REMOVE ALL JOINTS AND ASSOCIATED MAINTENANCE COSTS

On the back of a number of successful external container pavements and due to the busy nature of the facility and the fact that joints require maintenance. The Combi Slab solution was chosen because it removed all joints including saw cuts and dowelled joints, leaving a surface that requires little or no maintenance at all. 

Technical solution:

  • 325mm thick
  • Dramix 4D 65/60BG
  • Customised mesh

Benefits

The Combi Slab option removed all construction joints and saw-cuts, which meant the Combi Slab was constructed thinner than the alternative designs. The Combi Slab option also minimised any future maintenance of the slab by removing the joints which is the biggest maintenance cost for any slab.