Dramix only footings

Dramix optimized footings for Bunnings Joondalup

During the construction process BOSFA were asked to review the current reinforcing for the footings and if we could replace with Dramix fibres. BOSFA assessed all the footings and a Dramix fibre only solution was proposed and accepted by the builder.
The Dramix footings saved well over a week in fabrication time for the cages and significantly speed up the construction process.

Technical solution:

  • Dramix
  • No Reo
  • 32MPa
  • Bending moments satisfied

Benefits

No fabrication of cages
No Cranage for cages
Speed of placement
ease of placement

Dollar savings