Seamless Floors / Internal Slab

AUTO HANDLING FACILITY

DRAMIX 4D SEAMLESS FLOOR

Postal handling facility

25t post load

Restraint conditions

Client requirement no joints

Time restraints for const.

Technical solution:

  • Dramix 4D Combi Slab solution provided capacity for 25t post load
  • Removal of all joints.
  • 15,000m2 completed in 9 pours

Benefits

  • Major time savings
  • Improved building efficiencies, enabled builder to take delivery of conveyor system ahead of time.