A VICTORY FOR VICTO & DRAMIX

After seeing the benefits of using Dramix steel fibres in their footings for many years, Victo decided that they would be ideal for their latest larger warehouse project at Gilberton. Covering around 16,000m2 over three sheds, Prascon know Dramix fibres well, and specified the tried and tested 20kg/m3 dosage rate of the high-performing fibre for the jointless slabs in this project. Pourtek Concrete have been producing very high-quality finished slabs using the Wagners concrete supplied from their newest plant at Yatala, and everyone involved is very happy with the project.

Builder:                                – Victo
Engineer:                             – Prascon Consulting
Premix Supplier:                – Wagners Concrete
Contractor:                          – Pourtek Concrete

Technical solution:

  • Dramix Jointless Slab