DHL needed to expand their existing facility at Brisbane Airport, Dramix Slab-on-Piles provided the proven solution for the local ground conditions.
Tomkins Commercial and Industrial Builders have already built a couple of high quality Dramix 5D Slab-on-Piles projects at Brisbane Airport, and knew that it was again the right solution for the recently constructed expansion to the existing DHL facility. Tungsten Structures engineers were again on the project and worked with Keller to design this facility using their CMC piling system.
Builder: Tomkins Commercial and Industrial Builders
Engineer: Tungsten Structures
Concrete Contractor: McGinn Concrete
Concrete Supplier: Neilsens
Location: Brisbane Airport, QLD Australia
Technical solution:
- Dramix fibre only Slab-on-Piles using Dramix 5D high performance steel fibres.
Benefits
Dramix fibre only Jointless slabs eliminate the need for any saw-cuts. And by designing this facility with our structural high performance 5D fibres all additional loads associated with slab-on-piles design were easily accommodated.